SOC 2 timeline: how long does it take?

Last checked: 2026-10-16

Type 1 checks control design at a point in time; Type 2 checks operating effectiveness over an observation period (commonly 3–12 months). Sources give overlapping but different totals.

PhaseTypical duration (third-party estimates)
Readiness / prep1–3 months (Drata); 4–12 weeks (SOC2Auditors.io)
Observation period (Type 2 only)3–12 months
Auditor fieldwork2–5 weeks (Drata); 2–6 weeks (SOC2Auditors.io)
Report delivery2–6 weeks (Drata); 2–4 weeks (SOC2Auditors.io)
Total, Type 1About 2–6 months depending on source
Total, first Type 2About 6–15 months

Ranges vary by source and company. The AICPA doesn't prescribe a universal minimum observation period per one cited source. unverified

What speeds it up

Next: how much does SOC 2 cost?